Public Safety Training Center - Classroom Building
![Engineering Services](https://static.auburnalabama.org/media/apps/organization/facilityphoto/57/original.jpg)
Development Services Building
171 N Ross St
-
(334) 501-7390 -
[email protected] -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview New Facilities Renovations or Improvements
This project consists of the construction of an approximately 12,000 square foot multi-use classroom building for Public Safety. This is a main component of the Training Center master plan. It will allow effective training for Fire recruits, in-house continuing education for Fire and Police, and regional training partners to earn certifications from the State Fire College.
The project has a total capital budget of $4,800,000.00 and is anticipated to finish by Oct 31, 2024.
Status
- Design
- Bid Advertisement
- Contracts
- Construction
Drywall installation has been completed. Painting expected to begin end of May/beginning of June. Windows and app bay overhead doors have been installed. Air handling units have also been installed. Electrical overhead rough-in underway. Mezzanine flooring is currently being installed.